How is the construction of Victory Park Residences going?

Every month the elite houses of Victory Park Residences become more elegant and refined. All this happens because our specialists have optimized the construction process and perform all the work in parallel.

Earthworks and external construction works are almost 60% completed, reinforced concrete works are almost 80% completed, and foundation waterproofing is 57%. Almost 35% of the facade work in the project has been completed, now you can see how the active glazing of the buildings is going.

Finishing work continues in the houses, elevator systems are installed by a third, electrical and engineering communications are being carried out.